Skip to content

Electrical testing

We test switchgear, transformers, UPS systems and generators, and check that every breaker and relay trips at its setting before the system carries live IT load.

Request a test date
Pariksa engineers and the contractor's team at an open control panel with drives and breakers.

What the tests prove

A power system can look finished on the day it is energised and still hide a damaged cable, a breaker set to the wrong curve or a generator that cannot pick up its load, and each one only shows itself during a fault.

We test insulation and earthing while the system is dead, inject current into breakers and relays to time their trips, and run generators and UPS systems on load banks, comparing every reading with the design and the protection settings.

What we test

These are the tests most data center projects ask for, though your specification sets the final scope.

  • Insulation resistance

    Cables, busbars, switchgear and motor windings

  • Earthing

    Earth electrode resistance and earth continuity

  • Circuit breakers

    Trip tests and checks against the approved settings

  • Protection relays

    Secondary injection to time each trip

  • Transformers

    Turns ratio, winding resistance and insulation

  • Generators and motors

    Run tests under load

  • Power factor

    Measured at the main boards under load

  • Harmonics

    Logged with a power quality analyser

  • Load flow studies

    Voltage drop and loading across the network

  • Short circuit studies

    Fault levels checked against breaker ratings

Test before live load is connected

Insulation and protection tests are quick and safe while the system is dead, but once IT load is connected, every test needs a shutdown window.

  1. Installation complete

  2. Dead tests

  3. Energisation

  4. Load tests

  5. Integrated testing

Before we arrive

Send this list to your site team so the equipment is ready to test when we arrive.

  • Installation complete

    Equipment is installed, terminated and labelled, ready for inspection.

  • Isolation and permits

    An authorised person to isolate circuits, with permits to work issued.

  • Drawings and settings

    Single-line diagrams, cable schedules and the approved protection settings.

  • Load banks for load tests

    Load banks sized and connected for the generator and UPS tests.

  • Manufacturers and witnesses

    Manufacturer engineers on site, and your commissioning agent invited to witness.

What the report includes

Every test ends with a signed report that's ready to attach to the commissioning record, and your commissioning agent gets the same copy you do.

Ask for a sample report

Electrical test report

  1. 1Equipment tested, with a single-line diagram extract
  2. 2Insulation and earth resistance readings
  3. 3Breaker and relay trip times against settings
  4. 4Generator and UPS load test results
  5. 5Power quality and harmonic readings
  6. 6Equipment serial numbers and calibration dates
  7. 7Signatures of the tester and witnesses

Electrical tests on 3 projects

See all 3

Questions contractors ask

Do you need a shutdown?

Only for equipment that is already live, and we plan the windows with your facility team and test as much as we can before energising to keep them short.

Do you run power system studies?

Yes, we run load flow and short circuit studies from your single-line diagram, so breaker ratings and protection settings match the real fault levels.

What if a breaker or relay fails?

We record the result, check the setting with your electrical contractor and retest once it is corrected or the device is replaced.

How long does it take?

It depends on how much equipment is in scope and how ready it is. Once we have the single-line diagram, the test plan gives you an estimate.

Book electrical testing

Send the single-line diagram, the specification and your target dates, and we'll reply with a test plan and a quote.

Request a test date