Mechanical testing

We run chillers, CRAH units, pumps and fans at each load step and measure what they deliver, so you know every unit meets its design duty before handover.

Proves
Each unit delivers its design capacity
When
After start-up, before integrated testing
Method
Your approved test scripts and specification
You get
A signed report of design and measured values
A Pariksa engineer preparing instruments beside the chilled water pumps in a plant room.
Getting ready for a chilled water pump performance run.

What the test proves

A chiller or CRAH unit can start, run and show no alarms while still falling short of the capacity it was selected for. In a data hall, that shortfall shows up on the hottest day, with the IT load at its peak.

We run each unit at the load steps in the test script and record temperatures, flows, pressures and power. Every reading is compared with the equipment schedule and the manufacturer's data, and the unit passes or fails.

What we test

The test scripts set the exact steps. These are the units and checks they usually cover.

  • Chillers

    Capacity and efficiency at each load step

  • CRAH and CRAC units

    Cooling capacity, airflow and fan power

  • Air handling units

    Airflow, coil duty and pressure drop

  • Pumps

    Flow, head and power against the pump curve

  • Fans

    Airflow, pressure and power against the fan curve

  • Duty and standby

    Units swap over and restart as designed

  • Safeties and alarms

    Trips and interlocks respond as designed

  • Condition after the run

    Noise, vibration and temperatures checked

Test each unit before testing them together

Integrated testing assumes every chiller, CRAH unit and pump already meets its duty. A weak unit found then holds up the whole programme.

  1. Start-up

    Each unit is started by its manufacturer on permanent power.

  2. Performance test

    Units run at each load step while we measure. This is where we come in.

  3. Defects closed

    Anything short of design is fixed and retested.

  4. Integrated testing

    All systems run together through simulated failures.

  5. Handover

    The owner receives the plant with its test records.

Before we arrive

Send this list to your site team. A unit that is ready on the day is a unit that gets tested on the day.

  • Start-up signed off

    Each unit has been started by its manufacturer, with no open alarms.

  • Heat load in place

    Load banks or a real heat load, enough to run each unit at every step.

  • Test scripts approved

    Scripts, schedules and manufacturer's data, approved by your commissioning agent.

  • Controls engineer on call

    Someone who can change setpoints and override controls while we test.

  • Access and witnesses

    Safe access to each unit, and your commissioning agent invited to watch.

What the report includes

Every test ends with a signed report, ready to attach to the commissioning record. Your commissioning agent gets the same copy you do.

Ask for a sample report

Mechanical test report

  1. 1Units tested, with an equipment schedule extract
  2. 2Test scripts and load steps
  3. 3Capacity, flow, pressure and power at each step
  4. 4Results against design and manufacturer's data
  5. 5Punch list of anything that did not pass
  6. 6Equipment serial numbers and calibration dates
  7. 7Signatures of the tester and witnesses

Questions contractors ask

Which equipment do you test?

Chillers, CRAH and CRAC units, air handling units, pumps and fans. If a unit has a design duty on the equipment schedule, we can test it against that duty.

Where does the heat load come from?

A new data hall has no IT load yet, so the test runs on temporary load banks. The test plan says how much load each step needs.

What if a unit falls short?

We record the readings, check the setup with the manufacturer's engineer and add the unit to the punch list. Once it is fixed, we retest it.

How long does it take?

It depends on the number of units and load steps. Once we have the equipment schedule and the scripts, the test plan gives you an estimate.

Other tests we run

Book mechanical testing

Send the equipment schedule, the test scripts and your target dates. We reply with a test plan and a quote.