For low voltage installations, PUIL 2020 follows IEC 60364-6, which asks for at least 1 MΩ on circuits up to 500 V tested at 500 V DC, while NETA ATS Table 100.1, which many data center specifications name, asks for 100 MΩ on equipment rated 600 V or 1,000 V tested at 1,000 V DC. Accept the value the project specification names, and where it names both, test to the stricter one.
Why there are two sets of values
PUIL 2020 (SNI 0225:2020) is mandatory for installations in Indonesia and is based on the IEC 60364 series, so its insulation checks follow the IEC approach, in which a complete installation or circuit is tested as built and the minimum is low enough that a sound installation with long cable runs and many outlets will pass. NETA ATS starts from a different place, since it is an acceptance testing specification for individual pieces of equipment such as cables, switchgear, transformers and motors, and its minimums are set for new equipment tested on its own.
Data center specifications are often written by international design teams who name NETA ATS for equipment acceptance, while the local authority and the electrical contractor work to PUIL. On many projects both documents apply, and they give very different numbers for the same circuit, which is where most arguments over a megger reading start.
The two tables side by side
The first table gives the minimums in IEC 60364-6, the values PUIL 2020 is based on, which are set by the nominal voltage of the circuit.
| Circuit | Test voltage (DC) | Minimum insulation resistance |
|---|---|---|
| SELV and PELV | 250 V | 0.5 MΩ |
| Up to 500 V | 500 V | 1 MΩ |
| Above 500 V | 1,000 V | 1 MΩ |
SELV and PELV are separated and protective extra-low voltage circuits.
NETA ATS Table 100.1 sets the minimum by the voltage rating of the equipment rather than the voltage of the system, and its low voltage values are far higher because the equipment is new and tested alone.
| Equipment voltage rating | Test voltage (DC) | Minimum insulation resistance |
|---|---|---|
| 250 V | 500 V | 25 MΩ |
| 600 V | 1,000 V | 100 MΩ |
| 1,000 V | 1,000 V | 100 MΩ |

Which minimum applies
The project specification decides: where it names only PUIL or IEC, the IEC 60364-6 values are the acceptance limit, where it names NETA ATS for equipment acceptance, the NETA values apply to that equipment, and where it names both, test to the stricter of the two, which for low voltage cable and switchgear is the NETA figure.
Agree the acceptance value with the commissioning agent before testing starts and write it on the test sheet, so that a reading which passes one table and fails the other is settled in advance rather than argued over on the day.
Why a reading can differ from the table
Insulation resistance falls as temperature and humidity rise, so the same cable can read lower on a humid afternoon than on a dry morning. Length matters too, because a long run behaves like many short lengths of insulation in parallel and reads lower than a short one, and anything left connected, such as surge protective devices, meters, drives or UPS electronics, adds its own leakage path and pulls the reading down.
A low reading is therefore a reason to investigate before it is a reason to reject. Disconnect anything that should not be in the test, clean and dry the terminations and test again, and if the reading is still low, split the circuit into sections to find the one responsible.
What goes on the test sheet
A reading on its own cannot be checked or repeated, so we record it with everything needed to reproduce it.
- Circuit or equipment reference, matching the single-line diagram and cable schedule
- Test voltage and each conductor combination tested
- The reading for each combination and when in the test it was taken
- Ambient temperature and relative humidity
- Equipment disconnected for the test
- The acceptance value applied and the standard it comes from
- Instrument serial number and calibration date
- Date, tester and witness signatures
Questions about insulation resistance values
Which test voltage applies to a 400 V circuit?
Under IEC 60364-6 a 400 V circuit falls in the band up to 500 V, so it is tested at 500 V DC with a 1 MΩ minimum. Under NETA ATS the equipment rating counts instead, so cable or switchgear rated 600 V or 1,000 V is tested at 1,000 V DC with a 100 MΩ minimum.
Is the old "1,000 ohms per volt" rule still valid?
No, it comes from PUIL 2000, which PUIL 2020 replaced, and it gives a much lower figure than either current table. If a site procedure still quotes it, ask for the procedure to be updated to the value the specification names.
Does equipment have to be disconnected before the test?
Anything the test voltage could damage or that would give a false low reading should be, such as surge protective devices, electronic meters, drives, UPS electronics and control circuits. List what was disconnected on the test sheet, so the test can be repeated under the same conditions.
Why does the reading change with temperature?
Insulating materials conduct slightly more as they warm, and moist air settles on terminations and cable ends to add surface leakage, so readings taken in different conditions are only comparable when temperature and humidity are recorded with them. Some specifications also ask for readings to be corrected to a base temperature, and the test procedure should say how.
What about 20 kV cable?
Medium voltage cable is outside the low voltage tables above, and its acceptance values come from the project specification and the cable standard it names. Take the figure from those documents and agree it with the commissioning agent before testing.