Heat load testing a new data hall: what is measured at each load step

Mechanical testing

A heat load test places load banks in the data hall to stand in for the IT equipment, then raises the heat in steps up to the design load while the cooling plant runs as it will in service. At each step the supply and return air temperatures, airflow, chilled water flow and temperatures and power drawn are recorded, along with whether the controls hold their setpoints, and every reading is compared with the design data.

What a heat load test is

A new data hall has cooling but no IT load, so there is nothing to show that the CRAH units, chillers and pumps can carry the heat they were selected for. The heat load test fills that gap by placing load banks where the racks will stand, so they give off heat through the same airflow paths the IT equipment will use, and the project arranges them ahead of the test.

The load is raised in steps up to the design load, with the cooling plant running in its normal mode at each step. Testing in steps shows how the plant responds as the load grows, so a shortfall can be traced to the step and the unit where it first appears instead of showing up as a single failed reading at full load.

What is measured at each load step

Once the temperatures have settled at a step, we record the readings the test script asks for, which usually include:

  • Supply and return air temperatures at each CRAH unit
  • Airflow through each CRAH unit
  • Chilled water flow, with supply and return water temperatures, at the units and at the plant
  • Power drawn by the load banks and by the cooling equipment
  • Whether the controls hold the supply air and chilled water setpoints, and how the units modulate to do it

Readings are taken with calibrated instruments at the same points at every step, so the steps can be compared directly with each other and with the design.

A Pariksa engineer preparing instruments beside the chilled water pumps in a plant room.

How the readings are compared with the design

The power drawn by the load banks tells you how much heat went into the hall at each step. The heat each CRAH unit removed is worked out from its chilled water flow and the temperature difference across its coil, and checked against its airflow and air temperature difference, so the water side and air side confirm each other.

Each unit's measured duty is then compared with the equipment schedule and the manufacturer's data, and the hall's supply air temperatures are compared with the design conditions. When the heat removed matches the heat put in and every unit carries its share, the plant has shown it can handle that step; when it does not, the readings point to the unit or circuit that fell behind.

Where the test sits in the programme

The heat load test is functional testing, so it comes after the work that sets the conditions it measures. Testing, adjusting and balancing must be finished first, because a CRAH unit running at the wrong airflow or a coil on the wrong water flow will read short even if the unit itself is sound. The controls must also be commissioned, since the test judges whether they hold the setpoints under load.

Power to the load banks is the other dependency, as it needs a safe supply sized for the full design load before the first step can begin. The test then comes before the integrated systems test, which assumes the cooling already carries the design load.

What the report shows

The report lists the units tested with an extract of the equipment schedule, the test script and its load steps, and the readings at each step. It sets each unit's measured duty against the design and the manufacturer's data, records how the controls behaved, and lists anything that did not pass on a punch list for retest. Instrument serial numbers and calibration dates, and the signatures of the tester and witnesses, close the report, and your commissioning agent receives the same copy as you.

Questions about data hall heat load testing

Why test without the real IT load?

Waiting for the IT load means discovering any cooling shortfall with live servers in the hall, when every fix needs a shutdown. Load banks give a known, controlled heat that can be raised step by step and removed at any time.

What counts as a pass?

The readings at each step stay within the tolerances in the specification, covering each unit's duty, the supply air and chilled water temperatures and the controls holding their setpoints. A unit that falls outside them goes on the punch list and is retested once it is fixed.

Does the test cover failure scenarios such as a unit tripping?

No, the heat load test proves the plant carries the load in normal operation. Failure scenarios such as a unit tripping or a loss of power belong to the integrated systems test, which the commissioning agent leads.

What has to be finished before the test?

Besides balancing, controls and power, each unit needs its manufacturer's start-up signed off with no open alarms, the load banks must be placed where the racks will stand, and the commissioning agent must have approved the test script. A controls engineer should also be on site to change setpoints during the test.

How long does the plant run at each step?

The test script sets it, and the rule is to run long enough for the temperatures to settle so that the readings at each step are steady.